| Approx. Time Required | Description of Work |
| 4 Days | Site Preparation - Clear the land and install batter boards with string for reference |
| 4 Days | Excavation - Dig basement and trenches for footings, excavate trenches for water, sewer, gas and utility lines |
| 10 Days | Foundation - Pour all footing, pour/lay foundation walls, waterproof below grade, install drains, install perimeter insulation (optional) |
| 3 Days | Temporary Electric - Have electric company install temporary electric service before framing begins |
| 10 Days | Frame House - Install floor system, build and set exterior walls, frame roof system, set interior partitions, install exterior siding, install windows and exterior doors |
| 4 Days | Rough Plumbing - Locate plumbing fixtures and install all piping for sewer, water and gas lines |
| 5 Days | Heating/Air Conditioning - Install HVAC System and all ductwork |
| 5 Days | Rough Electric - Have electric company install meter. Install service panel, connect to meter and ground, run wiring to fixtures locations |
| 4 Days | Concrete Floors - Pour garage and basement pads after proper base and reinforcement has been installed. Outside patios should wait until drywall is finished |
| 8 Days | Insulation and Drywall - Install insulation, hang and finish drywall |
| 10 Days | Interior Finishing - Install interior doors, paint, install kitchen cabinets, bathroom vanities and all trim |
| 3 Days | Finish Electric, Plumbing and HVAC - Install light fixtures, receptacles, vent fans, doorbells, switch/receptacle plates, toiliets, sinks, faucets, vents and grills |
| 3 Days | Flooring/Carpeting - Install finish flooring and/or carpeting |